The
new Access Storage building in Basingstoke looks to all the
world like a state of the art new development. It is however
a comprehensive refurbishment of a deadly dull and neglected
pre-cast and glazed 60's office block. After an initial survey,
the Access Storage construction team, with MAA as concept architects,
concluded that refurbishment could provide the accommodation
they required at a fraction of the cost of demolition and new
build.
The
cladding of the building, which was carried out as a complete
envelope package by Westfield Roofing Limited, was an essential
element in the economics of the project. A complete new lift
shaft was constructed, with insulated panels from Architectural
Profiles Limited, linked directly into the structure of the
old building to provide an 'integrated' appearance.
As
a planning requirement the upstands of the building needed to
be raised to form parapets 2.3m above their existing level.
This presented a major problem as the existing nominal 500mm
pre-cast upstands possessed no structural strength. Architectural
Profiles provided the answer with their engineered 'Parapet
Cantilever System' which incorporates a lightweight galvanised
steel structural track formed into a compound section which
could cantilever over and past the existing weak upstands.
The
versatility of the structural track and fixing system was proved
time and time again, particularly when it was used to span over
existing 3m high windows which needed to be overclad to provide
a feature projection all the way around the building being capable
of supporting the cladding and the client's signage. Once the
structural issues were overcome the project became a simple
exercise using a designed combination of Architectural Profiles'
Half Round profiles and composite panels.
The
transformation of the building is nothing short of dramatic.
The raised perimeter of the building is now higher and displaying
proud signage with a striking colour scheme which is very pleasing
to the eye. The AP50HR profile cladding offset against the flat
paneling makes the building quite unique in its immediate location.
The transformation is now complete, achieved at minimum cost,
and proving that progress does not have to be at the expense
of the past.